Time to Update database
Moderators: i-Tree Support, i-Tree Team
-
- Posts: 2
- Joined: Mon Jul 18, 2022 11:34 pm
Time to Update database
How long does it take for species and pollution data to be updated on the i-Tree application after uploading to the database for a project in India
-
- i-Tree Team
- Posts: 341
- Joined: Fri Dec 21, 2012 7:45 am
Re: Time to Update database
We have improved our process so that database updates no longer require i-Tree Eco software updates to integrate new data. However, it will still typically take 2-3 months and can take as long as six months to integrate new location, precipitation, and/or pollution data into i-Tree Eco. The length of time depends largely on the length of the queue, the quality of the data submitted, and the workload on team members working on multiple ongoing projects.
Thanks,
Jason
Thanks,
Jason
A member of the i-Tree Team
-
- Posts: 2
- Joined: Mon Jul 18, 2022 11:34 pm
Re: Time to Update database
How long does it take to update species data only on i-Tree
-
- i-Tree Team
- Posts: 341
- Joined: Fri Dec 21, 2012 7:45 am
Re: Time to Update database
The timing is the same (typically 2-3 months) as it requires updates to the same underlying database that incorporates the local pollution data.
Thanks,
Jason
Thanks,
Jason
A member of the i-Tree Team