Time to Update database

Section for FAQs regarding i-Tree Database.

Moderators: i-Tree Support, i-Tree Team

Post Reply
tejaswi21371037
Posts: 2
Joined: Mon Jul 18, 2022 11:34 pm

Time to Update database

Post by tejaswi21371037 » Mon Jul 18, 2022 11:37 pm

How long does it take for species and pollution data to be updated on the i-Tree application after uploading to the database for a project in India
Jason.Henning
i-Tree Team
Posts: 337
Joined: Fri Dec 21, 2012 7:45 am

Re: Time to Update database

Post by Jason.Henning » Tue Jul 19, 2022 8:03 am

We have improved our process so that database updates no longer require i-Tree Eco software updates to integrate new data. However, it will still typically take 2-3 months and can take as long as six months to integrate new location, precipitation, and/or pollution data into i-Tree Eco. The length of time depends largely on the length of the queue, the quality of the data submitted, and the workload on team members working on multiple ongoing projects.
Thanks,
Jason
A member of the i-Tree Team
tejaswi21371037
Posts: 2
Joined: Mon Jul 18, 2022 11:34 pm

Re: Time to Update database

Post by tejaswi21371037 » Tue Jul 26, 2022 1:58 am

How long does it take to update species data only on i-Tree
Jason.Henning
i-Tree Team
Posts: 337
Joined: Fri Dec 21, 2012 7:45 am

Re: Time to Update database

Post by Jason.Henning » Tue Jul 26, 2022 8:45 am

The timing is the same (typically 2-3 months) as it requires updates to the same underlying database that incorporates the local pollution data.
Thanks,
Jason
A member of the i-Tree Team
Post Reply