Post by i-Tree Support » Tue Oct 18, 2011 8:29 pm

Yes, it is possible. The dialog box for manual data entry under the Enter or Edit data option has an "Add Plot" function which will add one plot to an existing set of plots. This option may be useful to create one or a few extra plots in the input database for an existing random sample project in progress.

See the attached document for a detailed example of recommended steps to add multiple plots to a previously processed stratified Eco project. The purpose of this may be to increase sampling intensity to improve estimates after an initial sample. http://www.itreetools.org/eco/resources ... edures.pdf